Order walkthrough · Guangzhou

A first collection, start to finish: 3 styles, 50 pieces each

Not a testimonial and not a case study with a logo on it — a walkthrough of what a small first order actually looks like, week by week, with the numbers that decide whether it works. Same shape for every first client, whether the label is new or twenty years old.

The brief

A brand with one season behind it and no production team wants three styles: a linen midi dress, a cotton poplin shirt and a wide-leg trouser. Fifty pieces per style, two colours, sizes S–L. Target retail $120–180, so landed cost has to stay under about $30 per unit. Launch date: ten weeks out.

That brief is deliberately ordinary. It is also the order most factories turn down, because 150 pieces across three styles is more setup than a container line wants.

Week 1 — specs, fabric, quote

DayWhat happens
1Three reference garments and a photo of a fabric they liked; no tech pack yet
2Fabric shortlist from stock: linen blend, cotton poplin, viscose twill — all available, no dye lot minimum
3–4Quote at 50 / 100 / 300 pieces per style, split into fabric, CMT, trims, packing, inspection
5They choose stock linen for the dress and a heavier poplin for the shirt; trousers move to viscose twill

The decision that saved the schedule: stock fabric instead of custom dyeing. It removed a 100–300 m dye lot minimum and two to four weeks. The cost of that decision is exclusivity — someone else could buy the same linen — which they accepted for a test drop.

Week 2–3 — sampling

Patterns are made from the reference garments plus measurements, then graded S–L. Proto samples arrive day 12. Two rounds of comments follow: the dress waist comes up 2 cm, the trouser rises 1.5 cm, the shirt cuff narrows. The third round is not needed because the comments were consolidated in one go rather than sent one at a time.

Where first orders lose a week: approval by email thread. Six comments, six replies, six days. One document with all comments, returned once, is the difference between ten weeks and eleven.

Week 4 — sign-off and deposit

Pre-production sample signed off, 30% deposit paid, fabric pulled from stock and inspected on receipt. Cutting date confirmed in writing — not "next week", but a date.

Week 5–8 — production

StageDaysNote
Cutting2Marker made for 50 pieces per style, two colours
Sewing, dress9Lined bodice, invisible zip
Sewing, shirt7Placket, collar, cuff — the slowest per minute
Sewing, trouser8Fly, waistband, pocket bags
Finishing2Thread trimming, pressing, hanging

Total production: 28 days, within the 25–35 quoted. Nothing was subcontracted; the three styles ran on the same floor so fabric and trims consolidated into one delivery.

Week 9 — inspection

150 pieces, every one measured, light-boxed, seam-checked and needle-detected. Eleven pieces came back on the first pass: seven for thread tails, three for a hem that waved, one for an off-centre collar. All were corrected in two days at our cost. The report went to the client before the balance was released, as it always does.

See what those checks look like — the tape, the light box and the rejects.

Week 10 — packing and shipping

Air freight for the first drop: 150 pieces, roughly 60 kg, about $480 door to door in Europe, seven days. Sea would have been $180 but six weeks — useless for a launch date. For this order the correct answer was air, and it was costed at quoting stage rather than discovered at the end.

The numbers

LineAmount
Goods, 150 pieces at $9.60–13.40 FOB$1,720
Sampling, 3 styles, 2 rounds$310
Labels, hangtags, polybags (300 sets)$180
Air freight to Europe$480
Total landed before duty$2,690
Landed cost per unit$17.90

At a $140 average retail price, that is a workable margin with room for returns and markdowns — which is the only reason a 150-piece first order makes sense at all.

What would have broken it

  • Custom-dyed fabric — plus two to four weeks, and a 100–300 m minimum per colour
  • Three separate factories — three deliveries, three inspections, three chances of a colour mismatch
  • Approval by email thread — the most common cause of a missed launch date, and it is the buyer's side
  • Sampling skipped to save $310 — moving fit decisions to the bulk order, where they cost the whole run

What comes next

If the dress sells, the reorder is 300 pieces in the same fabric: same pattern, no sampling, unit cost down 25–30%, production 20–30 days. That is where the money is — the first order is a test, the reorder is the business.

Questions we get asked

Is 150 pieces across three styles realistic?

Yes, if the styles share fabric decisions and run on the same floor. Three styles in three different fabrics, with three different factories, would cost far more in setup and inspection than the goods are worth.

How much of the ten weeks was production?

28 days of 70. The rest was sampling, approvals, inspection and shipping — which is why buyers who ask for "production in 20 days" usually get a shorter sampling window instead, and pay for it later.

Could this have been cheaper?

Yes: sea freight instead of air ($300 less), 300 pieces instead of 50 per style (25–30% lower unit cost), and stock trims instead of custom labels. Each one trades speed, cash or testing value — that is the actual decision, not the unit price.

What if the styles do not sell?

Then 150 pieces is a cheap answer to an expensive question. The alternative — 900 pieces across three styles to hit a factory minimum — is how first collections end up in a spare room.

Do you handle the shipping?

We hand over FOB Guangzhou, or book freight for you and quote it as a separate line. We do not hide freight inside the unit price; buyers who compare quotes need to see both numbers.

Can the reorder change fabric?

It can, but then it is a new style for costing purposes: new fabric, new lab dip, new sample. If the first fabric works, the second order is where you get the price break.

Request a quote

Four fields is enough to get a price.

Tell us what you want to make and how many pieces. You get FOB price, MOQ and a realistic lead time — answered by Belinda within one working day.

  • 50 pieces per style; no minimum on the first conversation
  • A photo, a sample or a full tech pack — all fine
  • Your details stay with us — no mailing list